The order is the part people get wrong: switch, fuse, load. The fuse protects the wire, so it goes at the source, not after the switch.
Sizing, in the order that matters
- Load current first. A 55 W lamp at 12 V is 4.6 A; a pump with 3x inrush is 14 A at start.
- Wire gauge for the run length. 1.5 mm2 is fine for 10 A over 3 m and marginal over 6 m; voltage drop shows up as a dim lamp or a slow pump.
- Fuse at 125-150 percent of continuous current, sized to the wire, not to the load.
- Switch last, and with the inrush in mind - a rocker that is fine on a lamp can weld on a motor.
Why the fuse goes before the switch
If the switch shorts internally or a wire chafes between switch and load, a fuse after the switch leaves that run unprotected. Put the fuse within 150 mm of the source terminal.
When to add a relay
Above roughly 10 A continuous, or with a motor or a compressor, drive a relay from the switch and let the relay take the load. The switch then only carries coil current and lasts its mechanical life instead of its electrical life.
The ground that is not a ground
On illuminated rockers the third pin is the lamp return, not earth. A 12 V LED switch wants that pin on negative; a 250 V neon wants neutral.
Field notes from a manufacturer. Full wiring detail on the 12 V switch wiring page, the 3-pin pinout on the 3 pin wiring page, index at answers.
Other notes in this series
- Reading a rocker switch nameplate: 16(4)A, T85/T125, 30 mOhm, IPX4 vs IPX6
- Cutouts, fuse holder sizes and inlets: 30x22 vs 19x13, 5x20 vs 6.3x32, C14 vs C20
- KCD4 30x22 cutout: panel thickness, tolerance, corner radius
- 3 pin rocker switch wiring: which pin is ground
- Switch inrush current: why a 16 A switch welds shut on an LED driver
- IP65, IP67, IP68 and NEMA 4: what the second digit does not promise
- AC vs DC switch ratings: why a 16 A AC switch is not a 16 A DC switch