Most small contractors find out a job lost money after the final invoice is paid. The numbers were there the whole time, but they sat in a timesheet app, a shoebox of receipts and someone's head.
You don't need software to fix that. A spreadsheet with three tabs and a handful of formulas will tell you, while the job is still running, whether it is on budget. This post builds one from scratch. Everything here works the same in Google Sheets and Excel.
The layout
Three tabs. Each one has a single job to do.
Jobs holds one row per job: what you quoted and what you expect it to cost.
| A | B | C | D | |
|---|---|---|---|---|
| 1 | Job ID | Name | Contract | Budget |
| 2 | J-101 | Kitchen remodel | 18500 | 12000 |
| 3 | J-102 | Deck rebuild | 9200 | 6500 |
| 4 | J-103 | Bathroom | 7400 | 5200 |
Time holds one row per shift: date, job ID, worker, hours, hourly rate, burden.
Costs holds one row per receipt or subcontractor invoice: date, job ID, category, amount.
The job ID is the only thing that connects the tabs. Type it the same way everywhere, or better, add a dropdown (Data > Data validation) that reads the IDs from the Jobs tab.
Formula 1: what an hour really costs
A worker paid $48 an hour does not cost you $48. Payroll taxes, workers' comp and insurance sit on top. That extra is called labor burden. It varies by trade and by state, so ask your accountant for your real number. The examples here use 25 percent.
On the Time tab, with hours in D, rate in E and burden in F:
=D2*E2*(1+F2) 40 hours at $48 with 25% burden is $2,400, not $1,920. If you skip burden, every job looks more profitable than it is.
Formula 2: labor per job
Back on the Jobs tab, column E adds up every Time row that belongs to the job:
=SUMIFS(Time!$G:$G, Time!$B:$B, $A2) Read it as: sum the cost column, but only the rows where the job ID matches this row's job ID.
Formula 3: everything else per job
Column F does the same for receipts and sub invoices:
=SUMIFS(Costs!$D:$D, Costs!$B:$B, $A2) Formula 4: actual cost, budget left, profit, margin
G2 =E2+F2 actual cost so far H2 =D2-G2 budget left I2 =C2-G2 gross profit if the job ended today J2 =IF(C2=0,"",I2/C2) gross margin The IF in the last one stops a blank row from showing a divide-by-zero error.
Formula 5: a flag you can read from across the room
=IF(A2="","",IF(G2>D2,"Over budget",IF(G2>0.9*D2,"Watch","OK"))) Add conditional formatting so "Over budget" turns red and "Watch" turns amber.
With some sample time and cost rows, the Jobs tab now looks like this:
| Job | Contract | Budget | Labor | Other | Actual | Budget left | Profit | Margin | Flag |
|---|---|---|---|---|---|---|---|---|---|
| Kitchen remodel | 18,500 | 12,000 | 3,840 | 7,300 | 11,140 | 860 | 7,360 | 39.8% | Watch |
| Deck rebuild | 9,200 | 6,500 | 6,075 | 2,400 | 8,475 | -1,975 | 725 | 7.9% | Over budget |
| Bathroom | 7,400 | 5,200 | 1,800 | 2,250 | 4,050 | 1,150 | 3,350 | 45.3% | OK |
The deck is the one to look at. It is still "profitable", but it has eaten almost all of its margin, and you can see that before the last invoice goes out, while there is still time to bill a change order or stop the overtime.
Three mistakes that break it quietly
Hours with no rate cost $0. If someone logs 8 hours for a new worker and the rate cell is empty, the row costs nothing and the job looks better than it is. Add a check column on the Time tab:
=IF(AND(D2>0,E2=0),"No rate","") Job IDs that almost match. J-101 and J-101 (with a trailing space) are different text, so SUMIFS skips the second one without any error. A dropdown prevents this.
Mixing change orders into the budget. If you raise the budget every time the client adds work, you lose the original estimate, and you can no longer tell a bad estimate from a job that grew. Keep change orders in their own list and add them to the contract value, not the budget.
Where the simple version runs out
This version tells you whether a job is over budget. It does not tell you why. For that you need the budget split by cost category (labor, materials, subs, permits), so you can see that the deck went over on labor and not on lumber. You also start wanting change orders, billing, and what you have invoiced compared with what you have earned.
All of that can be built with the same SUMIFS pattern and one more criteria pair for the category. If you would rather not build it, I sell a finished version with those parts in it: Job Cost Tracker for Contractors. The formulas above are the core of it, and they are enough to start today on a blank sheet.