Topics covered:
Oracle Database, Oracle AI Database, Oracle AutoUpgrade, Oracle Multi-tenant and Oracle Linux/Red Hat Enterprise Linux.
Who should read this?
Oracle Database Administrators, Database Engineers, Infrastructure Engineers and IT professionals.
Introduction
Upgrading Oracle Databases is a key function performed by DBAs. Whilst the basic functionality of an upgrade includes downloading and implementing new software there are many further factors to take into account.
These include: database structure, operating system support, database backup, application integration, security and recovery plus potentially even changes to database functionality.
I have recently investigated the upgrade from Oracle Database 19c to Oracle AI Database 26ai. This included examining how to utilise the AutoUpgrade tool and considering the requirements of a typical enterprise database setup.
Key queries to consider in an upgrade include:
Can you directly upgrade from Oracle Database 19c to Oracle AI Database 26ai?
Which Oracle tool should be used?
Must the source database be a CDB?
What occurs if the source is not a CDB?
What Linux checks need to be completed?
How can a DBA investigate upgrade issues?
How should the database and rollback processes be backed up?
What extra steps are needed if Oracle RAC and Data Guard are implemented?
Below I discuss supported upgrade options and provide a practical upgrade preparation and implementation guide.
Please note that the commands given are for educational purposes and should only be implemented within authorised test environments. They do not indicate that an upgrade has taken place within production.
- Oracle Database 19c and Oracle AI Database 26ai
Oracle Database 19c is commonly implemented. It provides functionality for enterprises including high availability, backup and recovery, and security.
Oracle AI Database 26ai is a more modern Oracle Database option which extends functionality but continues to also support relational and other data types.
Prior to an upgrade to Oracle AI Database 26ai, it is crucial for DBAs to recognise that a major version upgrade can cause changes in areas such as database structure, functionality and operation.
Importantly, Oracle AI Database 26ai implements a multi-tenant database structure. Within a Container Database (CDB), one or more Pluggable Databases (PDBs) can exist.
Hence, knowledge is needed regarding whether the source database is currently a CDB or not.
Understanding version numbers
Oracle AI Database 26ai may show that it is based upon Oracle Database software of the 23.26.x series.
For example, the version shown in documentation is 23.26.0.0.0 for Oracle AI Database 26ai.
However, this does not necessarily imply that there is a version inconsistency. There is often a distinction between Oracle’s external product nomenclature and the internal software version numbering.
DBAs should therefore check both the database software version and corresponding release documentation.
- Can Oracle Database 19c be directly upgraded to Oracle AI Database 26ai?
Yes. Oracle does approve a direct upgrade from an Oracle Database 19c to an Oracle AI Database 26ai.
Generally, there is therefore no requirement to first upgrade a supported Oracle 19c database to Oracle Database 21c.
Supported upgrade options
Source release | Upgrade to 26ai
--- | ---
Oracle Database 19c | Yes
Oracle Database 21c | Yes
Oracle Database 18c | No
Oracle Database 12c | No
Oracle Database 11g | No
Earlier versions may need to be upgraded or migrated in some way.
Nevertheless, just because Oracle does approve a version upgrade, this does not automatically signify that all operating systems, hardware, Grid Infrastructure versions and applications are certified for use with that upgrade.
Such items should therefore also be checked.
Further Oracle information: Database Releases That Support Direct Upgrade
- Understanding upgrade options
Oracle provides various methods by which databases can be upgraded or migrated.
When upgrading to Oracle AI Database 26ai, the two predominantly supported methods are AutoUpgrade and Replay Upgrade. Oracle Data Pump is also available for logical migration.
- AutoUpgrade
Oracle advises that AutoUpgrade should be utilised to prepare for and implement a supported upgrade.
It can:
Investigate the source database.
Detect upgrade issues.
Automatically apply supported fixes.
Manage the upgrade.
Implement post-upgrade functions.
Provide information relating to the upgrade.
Typically, I would initially use AutoUpgrade to prepare for a supported upgrade from a standard Oracle 19c CDB.
- Replay Upgrade
This is another supported upgrade method for 26ai.
It is especially pertinent for some multi-tenant and plug-in upgrade scenarios.
The exact process will depend upon the source and destination set up.
- Oracle Data Pump Migration
With Oracle Data Pump, DBAs can export and import supported database objects and data to a new environment.
This is a logical migration and so is not equivalent to an in-situ upgrade.
It can be beneficial for transitioning between environments, restructuring a database or for migrating selected application data.
Key point
Whilst AutoUpgrade, Replay Upgrade and Data Pump are all upgrade tools, they are not interchangeable.
The optimal choice will depend on factors such as the database structure, business needs, platform and allowable downtime. Recovery strategy is also a key consideration.
- Understanding CDB and non-CDB databases
It is important to firstly ascertain the type of database that is to be upgraded.
Log in to the Oracle 19c source database with an authorised administration account.
SELECT name, cdb, open_mode, log_mode FROM v$database; Understanding the output
If the CDB column has a value of YES, then the database is multi-tenant.
If, however, it has a value of NO, then the database is a non-CDB.
Scenario A – Upgrading a Oracle 19c CDB to a Oracle 26ai CDB
Provided that the Oracle 19c database is a CDB, it can be upgraded using an appropriately defined supported upgrade process.
Oracle 19c CDB | | AutoUpgrade v Oracle AI Database 26ai CDB | +--- PDB1 +--- PDB2 +--- Other PDBs Scenario B – Upgrading a Oracle 19c non-CDB to a Oracle 26ai database
A non-CDB cannot continue to be a non-CDB following an upgrade to Oracle AI Database 26ai. Instead a supported transformation or migration to a PDB must be undertaken.
Oracle 19c non-CDB | | Supported conversion | and upgrade procedure v Oracle 26ai CDB | v Oracle 26ai PDB This could for example involve first transforming the 19c non-CDB into a 19c PDB and/or using a supported transformation and upgrade procedure to convert it to a 26ai CDB.
Note: Transformation of a non-CDB into a PDB has differing requirements and recovery constraints to a CDB upgrade. Hence, a DBA must determine which transformation process should be followed prior to initiating AutoUpgrade.
- Upgrade environment understanding
Detail the source and destination environments.
A sample format for a planning sheet is shown below:
Component | Source | Destination
--- | --- | ---
Database release | Oracle 19c | Oracle AI Database 26ai
Database type | CDB/non-CDB | CDB/PDB
Operating system | Certified Linux version | Supported Linux version
Oracle Home | Oracle 19c home | Oracle 26ai home
Upgrade tool | - | Currently supported tool
Backup | Validated RMAN backup | Recovery plan in place
Application validation | Baseline information | Functional testing required
Downtime | Current availability requirements | Approved maintenance time slot
This table should accurately describe the environments in question, prior to undertaking an upgrade.
Operating system certification
Oracle Database must be checked to ensure that it is certified for the target operating system version and type.
On Red Hat Enterprise Linux, a DBA must not assume that a database version is certified for use simply because the relevant database installation software can be run. Certification should include verification of the operating system version, kernel and type. In addition, the database software and associated components must be checked.
For Oracle RAC, ASM and/or ACFS, further certification checks are also needed.
- Step 1 – Investigate the Oracle 19c environment
Initial information can be gathered regarding the source database.
Database version
SELECT banner_full FROM v$version; Database type
SELECT name, cdb, log_mode FROM v$database; Initial parameter investigation
SHOW PARAMETER compatible; As stated in Oracle’s 26ai upgrade documentation, the value of the database source COMPATIBLE parameter must be at least as high as the minimum supported version for the target database release.
For a direct upgrade to 26ai, the minimum supported source version is 19.0.0.
Do not alter this value without fully understanding the implications and having an approved process in place.
Database components
SELECT comp_id, comp_name, version, status FROM dba_registry ORDER BY comp_name; This assists in determining what database components are present and their current status.
Any existing component issues should be investigated.
Current SQL patches
SELECT patch_id, patch_type, action, status, action_time FROM dba_registry_sqlpatch ORDER BY action_time DESC; This aids in ascertaining the source database’s SQL patch status.
PDB information
If the source is a CDB then:
SELECT name, open_mode, restricted FROM v$pdbs; Note the PDBs and their current status.
Together, this information can be used to compare the source and upgraded databases.
- Step 2 – Investigate the Linux environment
Information about the Linux host’s operating system and kernel can be gathered.
Operating system
cat /etc/os-release On Red Hat Enterprise Linux:
cat /etc/redhat-release Kernel
uname -r System type
uname -m Disk space
df -h Memory
free -h Installed Oracle software
Within the appropriate Oracle Home:
$ORACLE_HOME/OPatch/opatch lsinventory This provides details of the Oracle software and patches which have been installed.
Why are these investigations significant?
Depending upon the upgrade, greater disk space capacity, new Oracle Homes and operating system packages, together with additional resources for maintenance, may be required.
Furthermore, a DBA should ensure that there is enough free disk space to accommodate upgrade, temporary and recovery-related information.
- Step 3 – Establish a validated recovery plan
No upgrade should be undertaken without a tested recovery plan in place.
Confirm that an appropriate backup currently exists.
Investigating RMAN backups
Start RMAN with an authorised login:
rman target / At the RMAN prompt enter:
LIST BACKUP SUMMARY; Validating backups
Where relevant for the environment:
RESTORE DATABASE VALIDATE; This ascertains whether RMAN can access the backup data which will be needed for a recovery.
Whilst successful backup validation is helpful, it does not in itself constitute a full test of a recovery process.
Example physical backup command
Assuming that the relevant environment has been correctly set up for ARCHIVELOG mode:
BACKUP DATABASE PLUS ARCHIVELOG; Whilst this command actually executes a backup, appropriate permissions, backup destinations and available disk space are needed. Again, this should not be implemented lightly within a production environment.
What should a recovery plan contain?
A recovery plan should address:
Database and control files.
Archived redo logs (if needed).
SPFILE and Oracle Net.
Encryption keystores and wallets (where relevant).
Access to backup media.
Recovery timescale.
Recovery point.
Application and service recovery.
A tested contingency process.
Whilst a guaranteed restore point can be an element of a rollback strategy, it should not be viewed as representing the whole approach.
Oracle cautions that, following certain stages of a non-CDB to PDB transformation, the original non-CDB state cannot automatically be recovered.
- Step 4 – Set up the Oracle AI Database 26ai environment
Oracle suggests that a distinct Oracle Home should be used for the target database version.
This should include the correct 26ai Oracle Database software and related updates for the target platform.
Typically, the set up process comprises:
Ensuring that the target operating system is certified.
Acquiring the appropriate Oracle AI Database software.
Installing this software within a new Oracle Home.
Applying the necessary or recommended Release Update.
Checking the installation and inventory.
Confirming that the correct Java runtime and AutoUpgrade tool are available.
Considering any required Grid Infrastructure and/or ASM upgrades.
Below are examples which make the assumption that both source and destination Oracle Homes have already been installed and are suitably configured.
Sample laboratory directories
Source Oracle Home: /u01/app/oracle/product/19c/dbhome_1 Target Oracle Home: /u01/app/oracle/product/26ai/dbhome_1 AutoUpgrade directory: /u01/app/oracle/autoupgrade Note that the names of Oracle Homes do not necessarily need to include ‘19c’ and/or ‘26ai’. Please use the relevant laboratory directory paths.
- Step 5 – Acquire the AutoUpgrade tool
Oracle recommends that the latest version of the relevant AutoUpgrade tool is used.
It is supplied in the form of a Java archive file called:
autoupgrade.jar Oracle publishes the most recent version of the AutoUpgrade tool within My Oracle Support Document 2485457.1.
Checking the tool version
Using a supported Java runtime:
java -jar autoupgrade.jar -version Why use the most up to date version?
Compared to older versions, a more recent AutoUpgrade tool may incorporate enhanced checks, fixes and also support for newer database versions.
Always ensure that the AutoUpgrade version is supported for both the source and target environments.
- Step 6 – Define the AutoUpgrade configuration
Within its configuration file, AutoUpgrade identifies the source database, source and destination Oracle Homes, and log directories.
The example shown below relates to a single instance Oracle 19c CDB upgrade to Oracle AI Database 26ai within a dedicated laboratory environment. Note that this is not for a non-CDB to PDB transformation.
lab19c_upgrade.cfg
global.autoupg_log_dir=/u01/app/oracle/autoupgrade/logs upg1.sid=LAB19C upg1.source_home=/u01/app/oracle/product/19c/dbhome_1 upg1.target_home=/u01/app/oracle/product/26ai/dbhome_1 upg1.log_dir=/u01/app/oracle/autoupgrade/logs/LAB19C Parameter Description
--- | ---
global.autoupg_log_dir | AutoUpgrade main log directory.
upg1.sid | Source database SID.
upg1.source_home | Source Oracle 19c home.
upg1.target_home | Destination Oracle AI Database home.
upg1.log_dir | Database specific AutoUpgrade log directory.
Key points
The configuration must accurately reflect the environment.
Depending on the situation, further configuration parameters may be required. For example, where a non-CDB is being transformed, for a RAC database, a Data Guard arrangement or cross-server migration is in place and/or there are complex PDB operations.
Prior to undertaking an upgrade, a DBA should compare the configuration with relevant Oracle documentation.
- Step 7 – Execute AutoUpgrade Analyse function
Undertaking the AutoUpgrade Analyse function is one of the most vital aspects of the upgrade procedure.
It identifies factors which may hinder, or could contribute to, an upgrade.
Command:
java -jar autoupgrade.jar \ -config /u01/app/oracle/autoupgrade/lab19c_upgrade.cfg \ -mode analyze Function of the Analyse function
AutoUpgrade investigates the source database and then generates reports which highlight points needing further investigation.
Such points may concern:
Database configuration.
Initialisation parameters.
Database components.
Tablespace and free space.
Time zones.
Unsupported features.
Upgrade suitability.
Plus other relevant information and cautions.
Why undertake the Analyse function?
Ideally, this should be done prior to the agreed maintenance period.
Following this, a DBA should examine the generated reports and address any issues which may impede an upgrade.
Key message
Although the AutoUpgrade Analyse function is not the actual upgrade process, it is a key preparatory stage.
Correct implementation is not simply determined by successfully executing the command. Rather, it is about effectively reviewing and dealing with the highlighted issues.
- Step 8 – Comprehend AutoUpgrade fixups
AutoUpgrade can automatically rectify some of the pre-upgrade issues that it detects.
These auto-correcting procedures are referred to as fixups.
Example command:
java -jar autoupgrade.jar \ -config /u01/app/oracle/autoupgrade/lab19c_upgrade.cfg \ -mode fixups Operation
Having analysed the source database, AutoUpgrade then carries out supported automatic fixes.
Not all issues can, however, be rectified in this manner. Some necessitate manual action, further planning and/or environmental changes.
Important note
In contrast to the Analyse function, the AutoUpgrade Fixups function can affect the source database. Thus, it should only be implemented following a DBA’s examination of the pre-upgrade report, confirmation that a suitable backup exists and receipt of appropriate authorisation to proceed.
Precautionary measures should also be taken to safeguard the source database.
- Step 9 – Implement the database upgrade
Having verified the upgrade, backup, infrastructure and pre-upgrade aspects, a deployment strategy can be formulated.
Within AutoUpgrade, the Deploy function is used to conduct the upgrade.
Example command:
java -jar autoupgrade.jar \ -config /u01/app/oracle/autoupgrade/lab19c_upgrade.cfg \ -mode deploy Warning: This is a genuine upgrade command. It has the potential to halt database services and alter database structure. Consequently, it should only be executed in an authorised test environment or within a defined production maintenance procedure, following successful test implementation.
Internal operation
The detailed upgrade process will vary according to the database type and configuration.
However, broadly speaking, the following steps occur:
Oracle 19c Database | v Pre-upgrade validation | v Required upgrade preparation | v Database upgrade processing | v Data dictionary changes | v Post-upgrade operations | v Database startup and checks | v Oracle AI Database 26ai Throughout this process, AutoUpgrade both implements and records progress.
Successful completion must be confirmed from both the AutoUpgrade and database outcomes.
Do not presume that a database upgrade has been successfully completed merely because an upgrade command has been executed.
- Step 10 – Review AutoUpgrade information
AutoUpgrade generates information relating to upgrade jobs and detailed log files.
Items for investigation include:
Upgrade job outcome.
Pre-upgrade cautions.
Errors and failed processes.
Fixup results.
Post-upgrade validation outcomes.
Any manual action which is required.
Exact file locations will depend on the configuration.
For the above example configuration, logs would be stored in the defined AutoUpgrade log directories.
Although the completion of an AutoUpgrade job is important, independent database and application validation should still be performed.
- Step 11 – Confirm Oracle AI Database version
Following successful laboratory upgrade implementation, connect to, and then check the target database.
Version
SELECT banner_full FROM v$version; Confirm that the software version corresponds to the anticipated Oracle AI Database 26ai version.
Bear in mind that, as mentioned previously, Oracle AI Database 26ai may show that it is based on Oracle Database software of the 23.26.x version series.
Database type
SELECT name, cdb, open_mode FROM v$database; PDBs
SELECT name, open_mode, restricted FROM v$pdbs; Components
SELECT comp_id, comp_name, version, status FROM dba_registry ORDER BY comp_name; Invalid objects
SELECT owner, object_type, COUNT(*) AS invalid_count FROM dba_objects WHERE status = 'INVALID' GROUP BY owner, object_type ORDER BY invalid_count DESC; Post-upgrade, some objects may require re-compilation. Adhere to Oracle’s documented re-compilation process and investigate any remaining invalid objects.
SQL patch information
SELECT patch_id, action, status, action_time FROM dba_registry_sqlpatch ORDER BY action_time DESC; When working with a CDB, relevant checks should also be made for PDBs as well as for the root container.
- Step 12. Check the Application and Operations
A database that reports the right version does not mean the upgrade is done from a business point of view.
Checking the application is a must.
Database checks
Make sure that:
Required databases and PDBs open without errors.
Expected database components are valid.
Required users and privileges are in place.
Application schemas can be accessed.
SQL patching and post-upgrade tasks are finished.
Performance checks
Compare the upgraded environment with the baseline you collected before the upgrade.
Areas to look at include:
SQL execution plans.
Resource consumption.
Application response times.
Database wait events.
Connection pool behavior.
Scheduled jobs.
Batch processing.
Backup checks
Review the RMAN configuration. Set the post-upgrade backup baseline that the recovery strategy requires.
Security checks
Validate:
Application authentication.
Database privileges.
Unified Auditing requirements.
Encryption and keystore access.
Database network connectivity.
Approved security configurations.
High availability checks
Where it applies, review RAC services, Data Guard status, monitoring and disaster recovery readiness.
The upgrade is complete in a sense only when the required database and application acceptance criteria are met.
- Special Points for Oracle RAC and ASM
Upgrading an Oracle Database is not the same as upgrading a database managed by Oracle Grid Infrastructure.
Oracle RAC environments bring in dependencies.
These include:
Oracle Clusterware.
Oracle Automatic Storage Management.
RAC database instances.
Cluster services.
Shared storage.
Cluster networking.
Grid Infrastructure compatibility.
Oracle requires a supported Grid Infrastructure release that fits the target database.
When needed, you must plan the required Grid Infrastructure upgrade before the database upgrade.
Important point
AutoUpgrade supports some Oracle RAC upgrade cases,. That does not mean every RAC major-version upgrade is rolling or free of downtime.
Oracle documentation describes the downtime requirements for the supported database upgrade workflow.
DBA tip
Start with a lab database to learn the upgrade stages.
Once you understand the process, build a RAC upgrade plan using the real cluster architecture and Oracle certification requirements.
- Special Points for Oracle Data Guard
Oracle Data Guard adds one important layer to database upgrades.
A primary database and its standby databases must stay within supported version and configuration requirements for the upgrade.
Before upgrading, review:
standby database versions.
Redo transport configuration.
Redo apply status.
Data Guard Broker configuration.
Network connectivity.
Standby recovery requirements.
Available. Backup capacity.
The supported Data Guard upgrade procedure.
AutoUpgrade supports certain Data Guard upgrade workflows.
The procedure is not the same as a simple standalone database upgrade.
Do not assume that upgrading the database automatically finishes all the standby database work you need.
A detailed upgrade and fallback plan must cover both sites.
- Understanding Upgrade Rollback and Downgrade
One of the important questions during a major-version upgrade is:
What happens if the new version does not work the way it should?
A DBA must tell three ideas apart.
Rollback
Going back to the state using an approved restore or upgrade recovery mechanism.
Recovery
Recovering the previous environment from a suitable RMAN backup and other recovery files you need.
Downgrade
Using a supported Oracle procedure to take an upgraded database back to a database release.
These are operations.
Not every upgrade or conversion case supports the fallback method.
Important warning about -CDB conversion
Oracle documentation warns in plain terms that automatic restoration to the original non-CDB state is no longer available after certain conversion stages.
So a verified backup and a separate recovery procedure are a must.
COMPATIBLE parameter point
Do not raise the database COMPATIBLE parameter to the release level without reviewing downgrade and recovery implications.
Oracle recommends keeping the compatible setting during the first round of post-upgrade validation where the documented upgrade procedure allows it.
The DBA should change compatibility only when it is the time and after business acceptance and recovery requirements have been reviewed.
- Common Upgrade Mistakes to Avoid
Mistake 1. Installing 26ai without checking certification
Installing the software does not prove support for the operating system, hardware or cluster configuration.
Mistake 2. Ignoring CDB and non-CDB differences
A 19c non-CDB needs a supported conversion or migration strategy.
Mistake 3. Skipping AutoUpgrade Analyze
This can leave upgrade issues hidden until the maintenance window.
Mistake 4. Assuming a RMAN backup proves recoverability
A reliable recovery plan needs backup verification and restore testing.
Mistake 5. Ignoring RAC and Data Guard dependencies
Enterprise database upgrades may touch infrastructure parts and systems.
Mistake 6. Changing COMPATIBLE early
Raising compatibility can limit downgrade options.
Mistake 7. Skipping application testing
A database that is technically upgraded can still have application performance, connectivity or compatibility problems.
Mistake 8. Claiming upgrade success without -upgrade validation
You should show upgrade completion through real job status, database checks and application acceptance results.
- My Practical DBA Upgrade Checklist
Before I try an Oracle 19c to upgrade, I would use this checklist.
Check
Requirement
Source version
Confirm Oracle Database 19c
Source architecture
Identify CDB or non-CDB
Target certification
Confirm OS, hardware and software support
Target Oracle Home
Install. Verify supported 26ai software
AutoUpgrade
Use the supported utility
COMPATIBLE
Confirm minimum source requirement
Database health
Review components and errors
RMAN backup
Verify backup and recovery readiness
Analyze mode
Complete and review reports
Fixups
Resolve required issues
Upgrade plan
Approve downtime and fallback
Deploy
Run only in an authorized environment
Post-upgrade checks
Verify database and PDB health
Application testing
Confirm expected functionality
Performance testing
Compare with the pre-upgrade baseline
Monitoring
Restore and validate monitoring coverage
Documentation
Record actual results and lessons learned
This structured approach helps cut operational risk and makes upgrades easier to repeat.
- Key Lessons for Oracle DBAs
Studying the Oracle 19c to upgrade path brings up several important lessons.
First, a supported direct upgrade does not remove the need for preparation.
The database version may be supported while another infrastructure part still needs changes.
Second, database architecture matters.
The gap between a CDB and non-CDB can change the upgrade workflow in a way.
Third, AutoUpgrade is more than an upgrade command.
Its analysis, fixup, deployment and diagnostic features help DBAs prepare for and control the process.
Fourth, backups and fallback planning are a must.
A database upgrade should never rest on guesses about recovery.
Fifth, a successful database startup is not enough.
The upgraded environment must be validated at the database, infrastructure and application levels.
Finally, an enterprise DBA should know not which commands to run but also why each stage is needed and what risks it covers.
Moving from Oracle Database 19c to Oracle AI Database 26ai is a modernization job that needs careful planning and technical prep.
Oracle supports an upgrade from 19c to 26ai and AutoUpgrade offers a recommended way to manage supported upgrade workflows.
Still, DBAs must understand the differences between CDB and non-CDB environments, check operating system and infrastructure compatibility, set up a recovery plan and test the upgraded database well.
For organizations that use RAC, ASM or Data Guard, the upgrade plan must also cover availability, storage, cluster infrastructure and disaster recovery needs.
My main takeaway from studying this upgrade path is:
A successful Oracle Database upgrade starts before AutoUpgrade runs and ends after technical validation, application acceptance and recovery readiness are confirmed.
Knowing the process, upgrade dependencies and possible failure cases is what makes database modernization safer and easier to predict.
Official Oracle References
- Oracle AI Database 26ai. Upgrade Guide
https://docs.oracle.com/en/database/oracle/oracle-database/26/upgrd/
- Database Releases That Support Direct Upgrade
- Choose an Upgrade Method for Oracle Database
- AutoUpgrade Processing Modes
- Understanding Non-CDB to PDB Upgrades
- Oracle Database Compatibility
- AutoUpgrade Configuration Options
About the Author
Abdulrawof Totakhil
Database Administrator | Oracle Database Linux | High Availability & Disaster Recovery
Focused on enterprise database administration, database performance, security, Oracle RAC, ASM, Data Guard, backup and recovery and infrastructure modernization.
Lets Connect & Share Knowledge
For talks, professional networking, working together or sharing what we know, feel free to reach me on LinkedIn.
LinkedIn: https://www.linkedin.com/in/abdulrawof-totakhil
Lets learn, share and grow together.