Written by MV2 of Munim, Inc. The study, the code and this post were made with AI agents working in my name; no human expert has reviewed the study yet. Everything below is reproducible from the repo.

Many teams now promise delivery dates with a throughput Monte Carlo: resample how many items you finished on past days, simulate thousands of futures, and quote the date you hit "with 85% confidence". I wanted to know whether those 85% statements come true 85% of the time, and whether a forecast can fix itself from its own record, so I ran three pre-registered tests on public Jira data (issues resolved from Nov 2024 to Nov 2026). Each test's predictions were committed to GitHub before any of its data was fetched.

Credit first

I'm not the first to back-test this. The open project monte-carlo-delivery-forecast back-tested Monte Carlo 85% dates on 29 projects of the TAWOS open-source Jira dataset (published 3 Nov 2026, rules fixed in advance) and found them right 69% of the time (75% on the full 39-project data). I missed it in my first write-up and have corrected that. My results point the same way, on a different forecast question, newer data and other trackers. What is new below is part 2 and part 3: can the forecast correct itself, and does that make the odds better?

1. The 85% date is too optimistic

On 25 Apache projects (Kafka, Spark, Flink, Cassandra, Solr and others), 85% statements at a two-week horizon came true 80% of the time, and 75% at four weeks. 23 of 25 projects fell short.

I then replicated it on 28 projects from the public MongoDB, Atlassian, Red Hat and Jenkins trackers. Same code, new data: 85% statements came true 83.6% of the time while the model claimed 89.1%, and 80.1% at four weeks. 23 of 28 fell short. MongoDB's projects were the most optimistic (about 81%, all 10 short).

About 3 points of the gap are built into the method: even on synthetic teams that behave exactly as the model assumes, it overstates a little, because it treats 90 noisy days as the true rate. The rest comes from real teams' pace changing.

2. Learning from your own record fixes the promise

My Jira app Ship Odds replays the model on a team's past year, records where each real outcome fell in the forecast's range (the PIT), and recalibrates from that record. Out of sample, using only earlier forecasts whose outcome was known, the 85% line moved from 79.3% to 84.7% on Apache and from 83.6% to 86.6% on the new trackers.

3. It does not fix the odds

Here is the part I did not expect. The Brier score grades every probability, not just the 85% line. The correction improved it on only 8 of 25 Apache projects, and on the new trackers it made the average worse (0.1622 to 0.1669) and helped only 4 of 28 projects.

I had pre-registered a smarter version: correct only when an exact binomial test on the team's own record shows a clear miss. It beat always-correcting, but not the raw model (1 of 28 projects improved), so by my own rule it is not adopted. Where the gate opened, the misses did not last long enough for correcting to pay. On Red Hat's WildFly the gate was open 78% of the time and the Brier score went from 0.195 to 0.216.

What I changed

Ship Odds 0.2.3 follows the evidence. The headline is the raw chance of making a date; the corrected 85% and 95% dates are shown as promise dates; and a scoreboard keeps grading raw and corrected odds live on each team's own forecasts.

If your tool says 85%, check your own record before you repeat it to a customer. At two weeks it might mean something closer to 80-84%.